Fire chief blames delays for increased fire hall costs

Oct. 30, 2012, Winnipeg - Winnipeg's fire-paramedic construction saga has grown even more complex as Chief Reid Douglas says project delays, not design changes, are responsible for the $2.3-million cost increase to Station No. 11. The Winnipeg Free Press reports.

October 30, 2012 
By The Winnipeg Free Press


Oct. 30, 2012, Winnipeg – Winnipeg's fire-paramedic construction saga has grown even more complex
as Chief Reid Douglas says project delays, not design changes, are
responsible for the $2.3-million cost increase to Station No. 11. The Winnipeg Free Press reports. | READ MORE